The following must be provided on the site at the time of inspection:
Inspection box and card must be located at the street, with the correct lot number posted.
Approved, stamped set of plans in the box along with truss and TJI documents, if used.
Any requested engineer letters must be provided at the time of inspection. Engineer letters must have the correct lot number and subdivision stated on the letter, with the engineer’s seal and signature. (Generic letters will not be accepted).
A port-a-john must be provided by the foundation inspection.
Handrails and guardrails must be provided on stairs and balconies during rough-ins.
Safe entry must be provided into the structure (no ramps).
All fire-stopping will be inspected at the framing stage.